Wellness and Rehabilitation Institute: Construction update for the week of April 13, 2015

Phase two, renovation of the east end of the Wellness and Rehabilitation Institute building, is now in progress.
  • Demolition of interior partitions is nearly complete.
  • New walls are being framed.
  • Mechanical and electrical rough-in is ongoing.
  • Sprinkler installation will begin soon.

In other campus improvement news, renovations of the nursing program facilities at Smyth Hall are underway.

  • Demolition continues.
  • Utilities are being removed and relocated.  There will be periodic shut downs for steam and water.