  • Landscaping is in progress at the west side of the building
  • Lawn areas on the north and west will be seeded this week
  • Final cleaning is taking place
  • AV equipment is being installed
  • Security cameras and card access devices are being installed
  • Punchlist items are being completed throughout
  • The greenhouse should be complete next week

Construction updates will continue to be posted here.

2 Responses to “Construction Update for the Week of 7/2/12”

  1. Linda Shriber July 3, 2012 at 9:41 pm #

    Hi Mike,
    I would like to see Occupational Therapy have a category choice on the side of the page so we can update people on the status of the OT lab and clinic

    • forcollegeandcommunity July 6, 2012 at 1:27 pm #

      Great suggestion, Linda — will do. Please send any updates that need posting to Sofia Tokar in marketing. She’ll work with you to get them up on the blog in a timely manner.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: