Construction Update for the Week of 6/18/12

18 Jun

The construction of the Integrated Center for Math and Science in Peckham Hall continues apace. This week the construction team will:

  • Generate the punchlist for the second floor
  • Complete punchlist items on the third floor
  • Undertake the final cleaning of the ground and first floors
  • Complete pre-functional testing for commissioning
  • Finalize elevator testing
  • Construct the greenhouse interior
  • Manage tunnel construction in front of Elizabeth George Hall
  • Work on the sidewalks at the west side of building
  • Continue landscaping
  • Hydroseed the east lawn

Updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: