  • Window installation should be mainly complete by the end of the month.
  • Brick installation is nearly complete with just the main entrance and the greenhouse remaining.
  • Slate roofing is also nearly complete with the flat roof being completed in the spring.
  • Painting has moved up to the first floor.
  • Drywall is being hung on the third floor.
  • The ceiling grid is being installed on the ground floor this week and will commence on the first floor next week.

Construction updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: