Construction Update for the Week of 1/9/12

6 Jan

Happy New Year! Here is the latest update on the construction of the Integrated Center for Math and Science:

  • The slate roofing on the west elevation is nearly complete.
  • Brickwork at the south end of the building and at the entry is ongoing.
  • Windows are being installed on the east elevation.
  • Painting is underway on the ground floor and will start on the first floor next week.
  • Drywall is being installed on the second and third floors.
  • Retaining wall construction is nearly complete.

Construction updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: