Construction Update for the Week of 12/5/11

2 Dec

Here is the latest construction update on the Integrated Center for Math and Science:

  • The brick installation will continue on the south end of the building through December.
  • The slate roofing is nearly complete on the east side of the building and will now continue on the west side.
  • Window installation is being changed to the week of December 19.
  • Construction of the greenhouse foundations has begun.
  • Most interior partitions are framed throughout the building and drywall is installed on the ground floor.
  • A campus-wide electrical shutdown is tentatively scheduled for approximately three hours on the morning of December 30.

Construction updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: