Construction Update for the Week of 11/7/11

4 Nov

Here is the latest construction update for the Integrated Center for Math and Science:

  • Roofing work continues and the simulated slate shingle installation will begin next week.
  • Brickwork on the east, north, and west elevations should be completed by the end of November.
  • Construction of the south retaining wall is complete; work continues on the west retaining wall.
  • Installation of windows will begin by Thanksgiving.
  • Installation of drywall will start in about two weeks on the ground floor and first floor once the roofing work is further along and the building is weather-tight.

Weekly construction updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: