Construction Update for Week of 8/22/11

19 Aug

Here is the latest construction update for the Integrated Center for Math and Science:

  • The exterior walls are currently under construction.  The metal framing and sheathing are nearly complete on the first floor and work has begun on the second floor.
  • The exterior brickwork has started on the northwest corner of the building.
  • The retaining wall at the west side of the building will be poured next week.
  • The concrete slab on the top floor will also be poured next week.
  • Framing for the roof will begin in early September.

Construction updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: