Construction Update for Week of 7/25/11

22 Jul

Here is the latest construction update for the Integrated Center for Math and Science:

  • Concrete floor slabs are going to be poured in sections twice a week for the next several weeks.
  • Structural steel work has stopped for now, but will resume on August 1 when the roof framing begins.
  • Construction on the retaining wall at the west side of the building will begin next week.
  • Fireproofing of the steel and framing of the exterior walls will also start next week.

A campus-wide electrical shutdown is scheduled for Saturday, August 6.  We are expecting this to last for up to 12 hours. Construction updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: