Construction Update for Week of 6/13/11

14 Jun

Construction on the Integrated Center for Math and Science continues throughout the summer.

Here is this week’s construction update:

  • Steel erection is well underway.
  • The first two floors of the building at the north end are nearly complete.  The contractor will be switching to the south end of the building later this week.
  • Construction of the tunnel connection continues.  The tunnel walls will be poured this week.
  • The utilities that are under the ground floor slab are being installed.

The construction team is tentatively trying to schedule an electrical shutdown to the campus on Sunday, June 26.  This is in addition to the shutdown we have scheduled for Saturday, August 6.

Construction updates will continue to be posted here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: