Construction Update for Week of 5/30/11

31 May

Here is this week’s construction update:

  • Construction of the new tunnel will begin May 31.
  • The foundation walls at the southwest corner of the building will be complete next week.
  • The water line serving the building will begin installation by the end of next week.
  • Construction of the retaining wall on the west side of the building will commence.
  • Structural steel will arrive on June 6.

Also, a reminder: We will have an electrical shut down for the entire campus on Saturday, August 6.

Check back here for continued construction updates.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: