Updates for the Week of April 11-15

11 Apr

Here are the current and upcoming construction activities for Math and Science:

  • Dust control- The weather at the ground breaking for the Integrated Center for Math on Science on April 11 raised our awareness for increased dust control on the site.  Sprinklers are being used to keep the dust down along the sidewalk and we are attempting to cover the large sand pile on the west side of the site to keep dust under control.
  • Footings are being poured along the west side of the building.
  • The first section of foundation wall was poured on the east side of the building last week.  The remaining section of the east wall will be formed this week.
  • There will be work going on adjacent to the sidewalk near the Psychology building later this week.  The contractors will be boring under the tunnel for a new storm water drainage pipe.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: