Site activities for the next couple of weeks include the following:

* The building excavation is now complete.
* Construction of the footings along the east side of the building is in progress.
* Footings will be complete in the next two weeks.
* The reinforcing steel for the foundation walls has begun at the southeast corner of the building.
* The relocation of the water line at the north end of the building will be complete next week.
* The area north of Elizabeth George will be seeded next week.
* Concrete trucks will make frequent deliveries over the next few weeks while the foundations are in progress.

Also, save the date for the official groundbreaking ceremony on Monday, April 11 at 10:30 a.m. The ceremony and reception will celebrate this historic undertaking with students, faculty, staff, alumni, and friends. Join us for this special occasion!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: