Wellness and Rehabilitation Institute: Construction update for the week of February 9, 2014

9 Feb

NAZRS151302_Sunset Construction 112114_001-scr

WRI Carroll Hall construction

WRI Carroll Hall construction

Interior spaces — including the elegant and welcoming lobby — are taking shape.  Other progress includes:

  • Flooring installation throughout the building.
  • Final coats of paint applied.
  • Ceilings are being dropped in.
  • Wood paneling installation in the lobby.
  • Mechanical, electrical, and plumbing work is nearly complete.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute: Construction update for the week of December 8, 2014

3 Dec
  • Most of the exterior work on the south and west sides of the building is complete.
  • Interior finishes continue.
  • Carpet is being installed, final painting has started, and ceilings are being installed.
  • Toilet rooms are nearing completion.
  • Cabinets and counters are installed.
  • Mechanical systems are operational.
  • Installation of light fixtures is continuing.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute: Construction update for the week of November 3, 2014

3 Nov

WRI construction

Framing the colorful view of campus in fall foliage, window trim is ongoing. Additionally, at the construction site:

  • Landscaping and site work on the south side of the building is nearly complete.
  • Parking, paving, and sidewalk construction continues on the west side of the building for the next two weeks.
  • Electrical and mechanical utility work will take place on the north side of the building.
  • Painting continues throughout the addition.
  • Lay-in ceilings are being installed.
  • Doors are being hung.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute: Construction update for the week of October 20, 2014

17 Oct

NAZRS147534_Construction 092314_042-scr

Inside and out, the new Wellness and Rehabilitation Institute is taking shape.

  • Landscaping is continuing along the south side of the building.
  • Sidewalks and brick paver installation along the east end of the addition is in progress.
  • Underground utilities and site work begins at the west end of the building.
  • Interior painting is ongoing throughout the addition.
  • Ceilings and light fixtures are being installed in the east half of the addition.
  • Mechanical and electrical rooms are being completed.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute: Construction update for the week of Sept. 22, 2014

19 Sep

Fresh paint and other exciting signs of progress at the construction site this week:

  • Site work continues with parking and side walks along the south side of the building.
  • Roofing of the addition will be ongoing for the next two weeks.
  • Window installation is nearly complete.
  • Brick at the west entry is in progress.
  • Drywall taping and finishing is taking place in the west half of the project.
  • Painting has already begun in the east half of the addition.
  • Ceiling installation will begin next week.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute: Construction Update, Week of September 8, 2014

4 Sep

WRI construction in Carroll Hall

 

 

 

 

 

 

 

 

 

  • With the exception of the west entry ramp and stair, the brick is nearly completed.
  • Windows on the south elevation will be completed shortly.
  • Installation of roofing materials begins.
  • Installation of the new storm water system is underway.
  • All the interior partitions are framed and most are drywalled.
  • Heating equipment, electrical, plumbing and sprinkler installation is ongoing.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute: Construction Update, Week of August 18, 2014

13 Aug

WRI construction

This week at the construction site:

  • Brick and window installation on the south elevation is nearly complete.
  • Storm water systems will be constructed over the next few weeks on the east and south sides of the building.
  • Interior partitions in the east half of the addition are almost complete.
  • Hanging of drywall on the partitions in the west half of the addition is underway.
  • Mechanical, electrical, and plumbing systems are in progress throughout the addition.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute: Construction Update, Week of July 21, 2014

21 Jul

NAZRS143274_Construction 071114_026-scrInterior spaces are taking shape now as work progresses to walls and windows.  This week at the construction site:

  • Brick installation continues along the east and west sides of the building.
  • Interior partitions are almost completely framed in the new addition.
  • Drywall is being hung in the east half of the addition.
  • Electrical and mechanical systems are being roughed in.
  • Windows will be delivered soon.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute Construction Update: Week of June 23, 2014

23 Jun

NAZRS142674_Construction 061814_006-scr

This week at the construction site:

  • Exterior wall framing continues.
  • Structural steel frame is complete.
  • Masonry wall construction is ongoing.
  • Concrete floor slabs will be poured on the ground floor.
  • Interior wall framing, duct installation and electrical rough in continues.

» For a live view of construction any time, visit our web cam.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Wellness and Rehabilitation Institute Construction Update: Week of June 16, 2014

13 Jun

This week at the construction site:

  • Exterior wall framing continues.
  • Air infiltration barrier is being applied.
  • Exterior brick is being installed at the east end.
  • Roofing of the new addition continues.
  • More concrete floor will be placed.
  • Interior partitions are being framed.
  • Sheet metal duct work is being hung.

» Web cam for a live view of construction any time.

» Learn more about the Nazareth College Wellness and Rehabilitation Institute.

Follow

Get every new post delivered to your Inbox.