Construction Update for the Week of 2/27/12

24 Feb

Here is the latest construction update on the Integrated Center for Math and Science:

  • Casework is being installed in the lab areas of the ground floor.
  • Installation of the elevator started today.
  • Window installation should be complete in about a week.
  • Work on the brick arches at the entry is ongoing.
  • Painting has started on the third floor.

Construction updates will continue to be posted here.