Happy New Year! Here is the latest update on the construction of the Integrated Center for Math and Science:
- The slate roofing on the west elevation is nearly complete.
- Brickwork at the south end of the building and at the entry is ongoing.
- Windows are being installed on the east elevation.
- Painting is underway on the ground floor and will start on the first floor next week.
- Drywall is being installed on the second and third floors.
- Retaining wall construction is nearly complete.