Construction Update for the Week of 5/21/12

21 May

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Construction of the reinforced sidewalk at the north side of the building will be ongoing for the next few weeks
  • Landscaping will begin at the south and east sides of the building toward the end of the week
  • The greenhouse is under construction
  • The expansion of Q Lot continues
  • Final painting is nearly complete
  • Final lab construction is in progress
  • Ceilings are nearly complete
  • The terrazzo floor in the lobby will be complete within the week

Construction updates will continue to be posted here.

Construction Update for the Week of 5/14/12

14 May

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Work at the north walkway will begin today
  • Q Lot expansion is ongoing
  • Final painting is nearly complete
  • The terrazzo floor in the lobby will be complete by Friday
  • Rubber flooring in the labs is nearly complete and corridor flooring is slated to start by Wednesday
  • Ceilings are complete throughout most of the building
  • Mechanical systems are running and being tested

Construction updates will continue to be posted here.

Construction Update for the Week of 5/07/12

7 May

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Site work continues along the east side of the building
  • Construction of the sidewalk along the north side of the building will begin soon
  • Ceiling installation is ongoing throughout
  • Final painting is nearly complete
  • Carpet is installed in the offices and rubber flooring is being installed in the labs
  • Building air handling systems are being started
  • Expansion of Q Lot begins this week

Construction updates will continue to be posted here.

Construction Update for the Week of 4/30/12

30 Apr

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Site work continues along the front of the building this week with sidewalks and grading
  • Final roofing is in progress
  • Carpet installation is nearly complete
  • Rubber flooring has started in the labs
  • Ceilings are being installed throughout on all floors
  • Plumbing fixtures are being installed
  • Air handling equipment will be operational this week

Construction updates will continue to be posted on this blog.

Construction Update for the Week of 4/16/12

18 Apr

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Paving of the parking area has started
  • Sidewalk installation on the east entrance has begun
  • Roofing is in progress
  • Window trim is being finished
  • Carpet installation will be complete in about a week
  • Painting is nearly complete
  • Lab construction is ongoing

Construction updates will continue to be posted here.

Voices for Autism Conference at Nazareth College, April 21

11 Apr

Autism has become one of the fastest-growing developmental disabilities in the U.S., affecting 1 in 88 children, and 1 in 54 boys. In response to the rapid rate this disability is occurring in the U.S., Nazareth College has partnered with CDS Monarch, a Rochester-based social service provider, to present the first Voices for Autism Conference on Saturday, April 21, 2012 from 8 a.m. to 3 p.m. in the Linehan Chapel, located in the Golisano Academic Center on the Nazareth campus. Author and advocate Dr. Paula Kluth will lead the keynote address. The cost is $40 for families/community members and $25 for students.

The conference will bring together the expertise and experiences of family members, professionals, and individuals on the spectrum in order to address a variety of topics relevant to promoting lifelong advocacy and self-advocacy for these individuals including: supporting communication, increasing knowledge regarding available services and supports, and developing strong supportive relationships across the community. Click here to learn more about this event and Dr. Kluth, as well as to register.

Construction Update for the Week of 4/9/12

9 Apr

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Brick cleaning and exterior details are nearing completion
  • Final window trim is being installed
  • Roofing of the flat roof areas is underway
  • Site work at the entrance is ongoing
  • Paving at the west side of the building and at the rear of the Psychology Building will begin next week
  • Laboratory fume hoods are being installed in the labs
  • Casework and counter tops are being installed throughout
  • Carpet and floor tile installation has started

Construction updates will continue to be posted here.

Construction Update for the Week of 4/2/12

30 Mar

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Finished site work has begun at the main entrance
  • Sidewalks will be poured this week
  • Window trim is nearly complete
  • Interior painting is nearly complete on all floors
  • Carpet installation will begin on the ground floor
  • Ceiling installation has started on the ground floor
  • Laboratory build-out is taking place on all floors
  • Ceramic tile is being installed in the toilet rooms
  • Mechanical, plumbing, and electrical work is ongoing throughout

Construction updates will continue to be posted here.

Construction Update for the Week of 3/12/12

8 Mar

Here is the latest update on the construction of the Integrated Center for Math and Science:

  • Laboratory casework is being installed on the first and second floors.
  • Painting is continuing throughout the building.
  • The elevator installation has begun.
  • The brick arched entrance will be complete in about a week and a half.
  • Exterior window trim is being installed.
  • Site work has resumed on the west side of the building.

Construction updates will continue to be posted here.

Construction Update for the Week of 2/27/12

24 Feb

Here is the latest construction update on the Integrated Center for Math and Science:

  • Casework is being installed in the lab areas of the ground floor.
  • Installation of the elevator started today.
  • Window installation should be complete in about a week.
  • Work on the brick arches at the entry is ongoing.
  • Painting has started on the third floor.

Construction updates will continue to be posted here.

Follow

Get every new post delivered to your Inbox.